WiRAD Project

Start:October 8, 2006
Finish:April 24, 2007
Report Date:October 8, 2006

Gantt Chart

WBS Name Work Week 41, 2006 Week 42, 2006 Week 43, 2006 Week 44, 2006 Week 45, 2006 Week 46, 2006 Week 47, 2006 Week 48, 2006 Week 49, 2006 Week 50, 2006 Week 51, 2006 Week 52, 2006 Week 2, 2007 Week 3, 2007 Week 4, 2007 Week 5, 2007 Week 6, 2007 Week 7, 2007 Week 8, 2007 Week 9, 2007 Week 10, 2007 Week 11, 2007 Week 12, 2007 Week 13, 2007 Week 14, 2007 Week 15, 2007 Week 16, 2007 Week 17, 2007
891011121314151617181920212223242526272829303112345678910111213141516171819202122232425262728293012345678910111213141516171819202122232425262728293031123456789101112131415161718192021222324252627282930311234567891011121314151617181920212223242526272812345678910111213141516171819202122232425262728293031123456789101112131415161718192021222324
1 Project Definition 3d
2 Mobile Robot - Research 11d
2.1 Search for feasibility of acquiring or building mobile robot 4d
2.2 Determine Hardware Requirements 3d
2.3 Determine Interfacing Options 3d
2.4 Determine Algorithm Requirements 2d
2.5 Determine Mobility Control 2d
2.6 Determine Energy Requirements 2d
2.7 Selection of Mobile Robot 1d
3 Mobile Robot - Implementation 34d
3.1 Robot Construction 14d
3.2 Algorithm Development 19d
3.2.1 Robot Localization 7d
3.2.2 Movement 7d
3.2.3 Connection Strength Management 7d
3.2.4 Power Management 7d
3.2.5 Signal Processing 7d
3.3 Interface Support 21d
4 Mobile Robot - Testing 14d
4.1 Algorithm Testing 14d
4.2 Bug Fixing 14d
5 WSN - Research 20d
5.1 Research and selection of WSN kit. 5d
5.2 Acquisition of WSN kit 14d
5.3 Determination of Communication between nodes 14d
5.4 Acquire online docs and materials for developing WSN. 14d
5.5 Determination of sensors to attach to nodes 14d
5.6 Determination of specifications of sensor devices and sensor nodes. 14d
6 WSN - Implementation 27d
6.1 Develop code for WSN communication 14d
6.2 Develop code for transfer of information between nodes 14d
7 WSN - Testing 14d
7.1 Test communication with several WSN 14d
7.2 Fix any bugs determined 14d
8 Integrated System - Integration 28d
8.1 Develop code for synchronization between mobile robot and WSN 28d
8.2 Develop code in the mobile robot to communicate with wireless sensor nodes. 28d
8.3 Develop code in the mobile robot for gap determination. 28d
8.4 Develop code in the mobile robot for localization. 28d
9 Integrated System - Testing 14d
9.1 Test integrated system with different gap scenarios 14d
9.2 Fix any bugs determined 14d
10 Integrated System - Finalization 21d
10.1 Onsite testing and ensure system is implemented in area of presentation. 21d
11 Integrated System - Presentation 21d
11.1 Produce posters for final presentation. 21d
11.2 Develop a video presentation. 21d

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Project Definition Oct 9 Oct 11 3d 0%
2 Mobile Robot - Research Oct 9 Oct 23 11d
2.1 Search for feasibility of acquiring or building mobile robot Oct 9 Oct 12 4d 0%
2.2 Determine Hardware Requirements Oct 12 Oct 16 3d 0%
2.3 Determine Interfacing Options Oct 17 Oct 19 3d 0%
2.4 Determine Algorithm Requirements Oct 20 Oct 23 2d 0%
2.5 Determine Mobility Control Oct 20 Oct 23 2d 0%
2.6 Determine Energy Requirements Oct 20 Oct 23 2d 0%
2.7 Selection of Mobile Robot Oct 20 Oct 20 1d 0%
3 Mobile Robot - Implementation Oct 20 Dec 6 34d
3.1 Robot Construction Oct 20 Nov 8 14d 0%
3.2 Algorithm Development Nov 8 Dec 4 19d
3.2.1 Robot Localization Nov 8 Nov 16 7d 0%
3.2.2 Movement Nov 8 Nov 16 7d 0%
3.2.3 Connection Strength Management Nov 16 Nov 24 7d 0%
3.2.4 Power Management Nov 16 Nov 24 7d 0%
3.2.5 Signal Processing Nov 24 Dec 4 7d 0%
3.3 Interface Support Nov 8 Dec 6 21d 0%
4 Mobile Robot - Testing Dec 6 Dec 25 14d
4.1 Algorithm Testing Dec 6 Dec 25 14d 0%
4.2 Bug Fixing Dec 6 Dec 25 14d 0%
5 WSN - Research Oct 9 Nov 3 20d
5.1 Research and selection of WSN kit. Oct 9 Oct 13 5d 0%
5.2 Acquisition of WSN kit Oct 17 Nov 3 14d 0%
5.3 Determination of Communication between nodes Oct 17 Nov 3 14d 0%
5.4 Acquire online docs and materials for developing WSN. Oct 17 Nov 3 14d 0%
5.5 Determination of sensors to attach to nodes Oct 17 Nov 3 14d 0%
5.6 Determination of specifications of sensor devices and sensor nodes. Oct 17 Nov 3 14d 0%
6 WSN - Implementation Nov 3 Dec 11 27d
6.1 Develop code for WSN communication Nov 3 Nov 22 14d 0%
6.2 Develop code for transfer of information between nodes Nov 22 Dec 11 14d 0%
7 WSN - Testing Dec 11 Dec 28 14d
7.1 Test communication with several WSN Dec 11 Dec 28 14d 0%
7.2 Fix any bugs determined Dec 11 Dec 28 14d 0%
8 Integrated System - Integration Jan 2 Feb 8 28d
8.1 Develop code for synchronization between mobile robot and WSN Jan 2 Feb 8 28d 0%
8.2 Develop code in the mobile robot to communicate with wireless sensor nodes. Jan 2 Feb 8 28d 0%
8.3 Develop code in the mobile robot for gap determination. Jan 2 Feb 8 28d 0%
8.4 Develop code in the mobile robot for localization. Jan 2 Feb 8 28d 0%
9 Integrated System - Testing Feb 8 Feb 27 14d
9.1 Test integrated system with different gap scenarios Feb 8 Feb 27 14d 0%
9.2 Fix any bugs determined Feb 8 Feb 27 14d 0%
10 Integrated System - Finalization Feb 27 Mar 27 21d
10.1 Onsite testing and ensure system is implemented in area of presentation. Feb 27 Mar 27 21d 0%
11 Integrated System - Presentation Mar 27 Apr 24 21d
11.1 Produce posters for final presentation. Mar 27 Apr 24 21d 0%
11.2 Develop a video presentation. Mar 27 Apr 24 21d 0%

Resources

Name Short name Type Group Email Cost
Doug Stamp Work WSN Group dstamp@yorku.ca 0
Hamdi Roumani Work WSN Group cs233017@cse.yorku.ca 0
Patrick Tayao Work Mobile Group ptayao@yorku.ca 0
Tyson Hamilton Work Mobile Group tyson@yorku.ca 0